PROJECT SCOPE:
Design and implementation of a potable water treatment system to reduce high municipal water costs and pressure-related leaks.
KEY SERVICES DELIVERED:
◦ Installation of a full water treatment plant
◦ Mechanical and electrical system integration
◦ Civil works including housing for treatment system
◦ Operations documentation and regulatory compliance
◦ Staff training and operational support for 6 months
MEASURED IMPACT:
◦ 750kL/month treatment plant capacity installed
◦ Pressure reduced from 9.18 bar to 3.00 bar, cutting leak risk
◦ Significantly reduced reliance on municipal water supply
R 382 000 saved on water bills every year!
Client
Bryneven Primary School
Location
Johannesburg, Gauteng, South Africa
Savings Achieved
R382 000 per year